Package XL01 aims to complete the Long Thanh bridge by the end of December 2026 and finish the entire package in March 2027. This package, part of the Ho Chi Minh City - Long Thanh expressway expansion project, spans nearly 10 km and is valued at nearly VND 5,600 billion. It is being implemented by a consortium led by Deo Ca Group.
This project was scheduled to begin in August 2025, but the site was not fully handed over until June 2026, significantly shortening the construction time.
A panoramic view of the Long Thanh bridge area, part of the Ho Chi Minh City - Long Thanh expressway expansion project, where construction is being accelerated.
PHOTO: TO CHI HUNG
To meet the deadline, the consortium of contractors mobilized nearly 900 personnel, more than 200 machines and equipment, and organized 33 construction teams, including 22 teams for elevated bridge construction, 5 teams for Long Thanh bridge construction, and 6 teams for girder casting.
Workers are busy with construction.
PHOTO: TO CHI HUNG
The teams were deployed simultaneously, maintaining continuous operation to complete the remaining work as planned. Taking advantage of every hour and every day, workers toiled tirelessly on the construction site to accelerate progress and compensate for the shortened construction time.
The Long Thanh bridge construction site viewed from above. To date, the progress of package XL01 has reached approximately 80%.
PHOTO: TO CHI HUNG
According to Mr. Nguyen Ngoc Lam, Executive Director of Package XL01 of the Ho Chi Minh City - Long Thanh Expressway Expansion Project, the overall progress of the package has reached approximately 80%. Specifically, the roadbed has been largely completed, the elevated bridge section has completed bored piles, and the substructure is nearly 98% complete. Beam installation is 92% complete, the first phase of bridge deck construction is 81% complete, and the railings are 43% complete.
The contractor for the Long Thanh bridge cantilever construction has completed 8 out of 85 segments.
PHOTO: TO CHI HUNG
For the Long Thanh Bridge (main bridge), the contractor has completed the construction of D2000 bored piles, pier foundations, pier shafts, and K0 pier tops. Cantilever casting has been carried out for 8 out of 85 segments, ensuring the bridge closure is on schedule.
An aerial view of the elevated section of the Ho Chi Minh City - Long Thanh expressway.
PHOTO: TO CHI HUNG
As for the elevated section and the Song Tac bridge, they will be completed in November 2026, facilitating traffic diversion for the repair of the old bridge surface.
Engineers inspect the construction techniques of the bridge deck for the Ho Chi Minh City - Long Thanh expressway expansion project.
PHOTO: TO CHI HUNG